Merges Phase 4a work including: Implementation: - Metadata discovery endpoint (/api/.well-known/oauth-authorization-server) - h-app microformat parser service - Enhanced authorization endpoint with client info display - Configuration management system - Dependency injection framework Documentation: - Comprehensive gap analysis for v1.0.0 compliance - Phase 4a clarifications on development approach - Phase 4-5 critical components breakdown Testing: - Unit tests for h-app parser (308 lines, comprehensive coverage) - Unit tests for metadata endpoint (134 lines) - Unit tests for configuration system (18 lines) - Integration test updates All tests passing with high coverage. Ready for Phase 4b security hardening.
633 lines
26 KiB
Markdown
633 lines
26 KiB
Markdown
# GAP ANALYSIS: v1.0.0 Roadmap vs Implementation
|
|
|
|
**Date**: 2025-11-20
|
|
**Architect**: Claude (Architect Agent)
|
|
**Analysis Type**: Comprehensive v1.0.0 MVP Verification
|
|
|
|
## Executive Summary
|
|
|
|
**Status**: v1.0.0 MVP is **INCOMPLETE**
|
|
|
|
**Current Completion**: Approximately **60-65%** of v1.0.0 requirements
|
|
|
|
**Critical Finding**: I prematurely declared v1.0.0 complete. The implementation has completed Phases 1-3 successfully, but **Phases 4 (Security & Hardening) and Phase 5 (Deployment & Testing) have NOT been started**. Multiple P0 features are missing, and critical success criteria remain unmet.
|
|
|
|
**Remaining Work**: Estimated 10-15 days of development to reach v1.0.0 release readiness
|
|
|
|
---
|
|
|
|
## Phase-by-Phase Analysis
|
|
|
|
### Phase 1: Foundation (Week 1-2)
|
|
|
|
**Status**: **COMPLETE** ✅
|
|
|
|
**Required Features**:
|
|
1. Core Infrastructure (M) - ✅ COMPLETE
|
|
2. Database Schema & Storage Layer (S) - ✅ COMPLETE
|
|
3. In-Memory Storage (XS) - ✅ COMPLETE
|
|
4. Email Service (S) - ✅ COMPLETE
|
|
5. DNS Service (S) - ✅ COMPLETE
|
|
|
|
**Exit Criteria Verification**:
|
|
- ✅ All foundation services have passing unit tests (96 tests pass)
|
|
- ✅ Application starts without errors
|
|
- ✅ Health check endpoint returns 200
|
|
- ✅ Email can be sent successfully (tested with mocks)
|
|
- ✅ DNS queries resolve correctly (tested with mocks)
|
|
- ✅ Database migrations run successfully (001_initial_schema)
|
|
- ✅ Configuration loads and validates correctly
|
|
- ✅ Test coverage exceeds 80% (94.16%)
|
|
|
|
**Gaps**: None
|
|
|
|
**Report**: /home/phil/Projects/Gondulf/docs/reports/2025-11-20-phase-1-foundation.md
|
|
|
|
---
|
|
|
|
### Phase 2: Domain Verification (Week 2-3)
|
|
|
|
**Status**: **COMPLETE** ✅
|
|
|
|
**Required Features**:
|
|
1. Domain Service (M) - ✅ COMPLETE
|
|
2. Email Verification UI (S) - ✅ COMPLETE
|
|
|
|
**Exit Criteria Verification**:
|
|
- ✅ Both verification methods work end-to-end (DNS TXT + email fallback)
|
|
- ✅ TXT record verification preferred when available
|
|
- ✅ Email fallback works when TXT record absent
|
|
- ✅ Verification results cached in database (domains table)
|
|
- ✅ UI forms accessible and functional (templates created)
|
|
- ✅ Integration tests for both verification methods (98 tests, 71.57% coverage on new code)
|
|
|
|
**Gaps**: Endpoint integration tests not run (deferred to Phase 5)
|
|
|
|
**Report**: /home/phil/Projects/Gondulf/docs/reports/2025-11-20-phase-2-domain-verification.md
|
|
|
|
---
|
|
|
|
### Phase 3: IndieAuth Protocol (Week 3-5)
|
|
|
|
**Status**: **PARTIALLY COMPLETE** ⚠️ (3 of 4 features complete)
|
|
|
|
**Required Features**:
|
|
1. Authorization Endpoint (M) - ✅ COMPLETE
|
|
2. Token Endpoint (S) - ✅ COMPLETE
|
|
3. **Metadata Endpoint (XS) - ❌ MISSING** 🔴
|
|
4. Authorization Consent UI (S) - ✅ COMPLETE
|
|
|
|
**Exit Criteria Verification**:
|
|
- ✅ Authorization flow completes successfully (code implemented)
|
|
- ✅ Tokens generated and validated (token service implemented)
|
|
- ❌ **Metadata endpoint NOT implemented** 🔴
|
|
- ❌ **Client metadata NOT displayed correctly** 🔴 (h-app microformat fetching NOT implemented)
|
|
- ✅ All parameter validation working (implemented in routers)
|
|
- ✅ Error responses compliant with OAuth 2.0 (implemented)
|
|
- ❌ **End-to-end tests NOT run** 🔴
|
|
|
|
**Critical Gaps**:
|
|
|
|
1. **MISSING: `/.well-known/oauth-authorization-server` metadata endpoint** 🔴
|
|
- **Requirement**: v1.0.0 roadmap line 62, Phase 3 line 162, 168
|
|
- **Impact**: IndieAuth clients may not discover authorization/token endpoints
|
|
- **Effort**: XS (<1 day per roadmap)
|
|
- **Status**: P0 feature not implemented
|
|
|
|
2. **MISSING: Client metadata fetching (h-app microformat)** 🔴
|
|
- **Requirement**: Success criteria line 27, Phase 3 line 169
|
|
- **Impact**: Consent screen cannot display client app name/icon
|
|
- **Effort**: S (1-2 days to implement microformat parser)
|
|
- **Status**: P0 functional requirement not met
|
|
|
|
3. **MISSING: End-to-end integration tests** 🔴
|
|
- **Requirement**: Phase 3 exit criteria line 185, Testing Strategy lines 282-287
|
|
- **Impact**: No verification of complete authentication flow
|
|
- **Effort**: Part of Phase 5
|
|
- **Status**: Critical testing gap
|
|
|
|
**Report**: /home/phil/Projects/Gondulf/docs/reports/2025-11-20-phase-3-token-endpoint.md
|
|
|
|
---
|
|
|
|
### Phase 4: Security & Hardening (Week 5-6)
|
|
|
|
**Status**: **NOT STARTED** ❌
|
|
|
|
**Required Features**:
|
|
1. Security Hardening (S) - ❌ NOT STARTED
|
|
2. Security testing - ❌ NOT STARTED
|
|
|
|
**Exit Criteria** (NONE MET):
|
|
- ❌ All security tests passing 🔴
|
|
- ❌ Security headers verified 🔴
|
|
- ❌ HTTPS enforced in production 🔴
|
|
- ❌ Timing attack tests pass 🔴
|
|
- ❌ SQL injection tests pass 🔴
|
|
- ❌ No sensitive data in logs 🔴
|
|
- ❌ External security review recommended (optional but encouraged)
|
|
|
|
**Critical Gaps**:
|
|
|
|
1. **MISSING: Security headers implementation** 🔴
|
|
- No X-Frame-Options, X-Content-Type-Options, Strict-Transport-Security
|
|
- No Content-Security-Policy
|
|
- **Requirement**: Success criteria line 44, Phase 4 deliverables line 199
|
|
- **Impact**: Application vulnerable to XSS, clickjacking, MITM attacks
|
|
- **Effort**: S (1-2 days)
|
|
|
|
2. **MISSING: HTTPS enforcement** 🔴
|
|
- No redirect from HTTP to HTTPS
|
|
- No validation that requests are HTTPS in production
|
|
- **Requirement**: Success criteria line 44, Phase 4 deliverables line 198
|
|
- **Impact**: Credentials could be transmitted in plaintext
|
|
- **Effort**: Part of security hardening (included in 1-2 days)
|
|
|
|
3. **MISSING: Security test suite** 🔴
|
|
- No timing attack tests (token comparison)
|
|
- No SQL injection tests
|
|
- No XSS prevention tests
|
|
- No open redirect tests
|
|
- No CSRF protection tests
|
|
- **Requirement**: Phase 4 lines 204-206, Testing Strategy lines 289-296
|
|
- **Impact**: Unknown security vulnerabilities
|
|
- **Effort**: S (2-3 days per roadmap line 195)
|
|
|
|
4. **MISSING: Constant-time token comparison verification** 🔴
|
|
- Implementation uses SHA-256 hash comparison (good)
|
|
- But no explicit tests for timing attack resistance
|
|
- **Requirement**: Phase 4 line 200, Success criteria line 32
|
|
- **Impact**: Potential timing side-channel attacks
|
|
- **Effort**: Part of security testing
|
|
|
|
5. **MISSING: Input sanitization audit** 🔴
|
|
- **Requirement**: Phase 4 line 201
|
|
- **Impact**: Potential injection vulnerabilities
|
|
- **Effort**: Part of security hardening
|
|
|
|
6. **MISSING: PII logging audit** 🔴
|
|
- **Requirement**: Phase 4 line 203
|
|
- **Impact**: Potential privacy violations
|
|
- **Effort**: Part of security hardening
|
|
|
|
**Report**: NONE (Phase not started)
|
|
|
|
---
|
|
|
|
### Phase 5: Deployment & Testing (Week 6-8)
|
|
|
|
**Status**: **NOT STARTED** ❌
|
|
|
|
**Required Features**:
|
|
1. Deployment Configuration (S) - ❌ NOT STARTED
|
|
2. Comprehensive Test Suite (L) - ❌ PARTIALLY COMPLETE (unit tests only)
|
|
3. Documentation review and updates - ❌ NOT STARTED
|
|
4. Integration testing with real clients - ❌ NOT STARTED
|
|
|
|
**Exit Criteria** (NONE MET):
|
|
- ❌ Docker image builds successfully 🔴
|
|
- ❌ Container runs in production-like environment 🔴
|
|
- ❌ All tests passing (unit ✅, integration ⚠️, e2e ❌, security ❌)
|
|
- ❌ Test coverage ≥80% overall, ≥95% for critical code (87.27% but missing security tests)
|
|
- ❌ Successfully authenticates with real IndieAuth client 🔴
|
|
- ❌ Documentation complete and accurate 🔴
|
|
- ❌ Release notes approved ❌
|
|
|
|
**Critical Gaps**:
|
|
|
|
1. **MISSING: Dockerfile** 🔴
|
|
- No Dockerfile exists in repository
|
|
- **Requirement**: Success criteria line 36, Phase 5 deliverables line 233
|
|
- **Impact**: Cannot deploy to production
|
|
- **Effort**: S (1-2 days per roadmap line 227)
|
|
- **Status**: P0 deployment requirement
|
|
|
|
2. **MISSING: docker-compose.yml** 🔴
|
|
- **Requirement**: Phase 5 deliverables line 234
|
|
- **Impact**: Cannot test deployment locally
|
|
- **Effort**: Part of deployment configuration
|
|
|
|
3. **MISSING: Backup script for SQLite** 🔴
|
|
- **Requirement**: Success criteria line 37, Phase 5 deliverables line 235
|
|
- **Impact**: No operational backup strategy
|
|
- **Effort**: Part of deployment configuration
|
|
|
|
4. **MISSING: Environment variable documentation** ❌
|
|
- .env.example exists but not comprehensive deployment guide
|
|
- **Requirement**: Phase 5 deliverables line 236
|
|
- **Impact**: Operators don't know how to configure server
|
|
- **Effort**: Part of documentation review
|
|
|
|
5. **MISSING: Integration tests for endpoints** 🔴
|
|
- Only 5 integration tests exist (health endpoint only)
|
|
- Routers have 29-48% coverage
|
|
- **Requirement**: Testing Strategy lines 275-280, Phase 5 line 230
|
|
- **Impact**: No verification of HTTP request/response cycle
|
|
- **Effort**: M (3-5 days, part of comprehensive test suite)
|
|
|
|
6. **MISSING: End-to-end tests** 🔴
|
|
- No complete authentication flow tests
|
|
- **Requirement**: Testing Strategy lines 282-287
|
|
- **Impact**: No verification of full user journey
|
|
- **Effort**: Part of comprehensive test suite
|
|
|
|
7. **MISSING: Real client testing** 🔴
|
|
- Not tested with any real IndieAuth client
|
|
- **Requirement**: Success criteria line 252, Phase 5 lines 239, 330
|
|
- **Impact**: Unknown interoperability issues
|
|
- **Effort**: M (2-3 days per roadmap line 231)
|
|
|
|
8. **MISSING: Documentation review** ❌
|
|
- Architecture docs may be outdated
|
|
- No installation guide
|
|
- No configuration guide
|
|
- No deployment guide
|
|
- No troubleshooting guide
|
|
- **Requirement**: Phase 5 lines 229, 253, Release Checklist lines 443-451
|
|
- **Effort**: M (2-3 days per roadmap line 229)
|
|
|
|
9. **MISSING: Release notes** ❌
|
|
- **Requirement**: Phase 5 deliverables line 240
|
|
- **Impact**: Users don't know what's included in v1.0.0
|
|
- **Effort**: S (<1 day)
|
|
|
|
**Report**: NONE (Phase not started)
|
|
|
|
---
|
|
|
|
## Feature Scope Compliance
|
|
|
|
Comparing implementation against P0 features from v1.0.0 roadmap (lines 48-68):
|
|
|
|
| Feature | Priority | Status | Evidence | Gap? |
|
|
|---------|----------|--------|----------|------|
|
|
| Core Infrastructure | P0 | ✅ COMPLETE | FastAPI app, config, logging | No |
|
|
| Database Schema & Storage Layer | P0 | ✅ COMPLETE | SQLAlchemy, 3 migrations | No |
|
|
| In-Memory Storage | P0 | ✅ COMPLETE | CodeStore with TTL | No |
|
|
| Email Service | P0 | ✅ COMPLETE | SMTP with TLS support | No |
|
|
| DNS Service | P0 | ✅ COMPLETE | dnspython, TXT verification | No |
|
|
| Domain Service | P0 | ✅ COMPLETE | Two-factor verification | No |
|
|
| Authorization Endpoint | P0 | ✅ COMPLETE | /authorize router | No |
|
|
| Token Endpoint | P0 | ✅ COMPLETE | /token router | No |
|
|
| **Metadata Endpoint** | **P0** | **❌ MISSING** | **No /.well-known/oauth-authorization-server** | **YES** 🔴 |
|
|
| Email Verification UI | P0 | ✅ COMPLETE | verify_email.html template | No |
|
|
| Authorization Consent UI | P0 | ✅ COMPLETE | authorize.html template | No |
|
|
| **Security Hardening** | **P0** | **❌ NOT STARTED** | **No security headers, HTTPS enforcement, or tests** | **YES** 🔴 |
|
|
| **Deployment Configuration** | **P0** | **❌ NOT STARTED** | **No Dockerfile, docker-compose, or backup script** | **YES** 🔴 |
|
|
| Comprehensive Test Suite | P0 | ⚠️ PARTIAL | 226 unit tests (87.27%), no integration/e2e/security | **YES** 🔴 |
|
|
|
|
**P0 Features Complete**: 11 of 14 (79%)
|
|
**P0 Features Missing**: 3 (21%)
|
|
|
|
---
|
|
|
|
## Success Criteria Assessment
|
|
|
|
### Functional Success Criteria (Line 22-28)
|
|
|
|
| Criterion | Status | Evidence | Gap? |
|
|
|-----------|--------|----------|------|
|
|
| Complete IndieAuth authentication flow | ⚠️ PARTIAL | Authorization + token endpoints exist | Integration not tested |
|
|
| Email-based domain ownership verification | ✅ COMPLETE | Email service + verification flow | No |
|
|
| DNS TXT record verification (preferred) | ✅ COMPLETE | DNS service working | No |
|
|
| Secure token generation and storage | ✅ COMPLETE | secrets.token_urlsafe + SHA-256 | No |
|
|
| **Client metadata fetching (h-app microformat)** | **❌ MISSING** | **No microformat parser implemented** | **YES** 🔴 |
|
|
|
|
**Functional Completion**: 4 of 5 (80%)
|
|
|
|
### Quality Success Criteria (Line 30-34)
|
|
|
|
| Criterion | Status | Evidence | Gap? |
|
|
|-----------|--------|----------|------|
|
|
| 80%+ overall test coverage | ✅ COMPLETE | 87.27% coverage | No |
|
|
| 95%+ coverage for authentication/token/security code | ⚠️ PARTIAL | Token: 91.78%, Auth: 29.09% | Integration tests missing |
|
|
| **All security best practices implemented** | **❌ NOT MET** | **Phase 4 not started** | **YES** 🔴 |
|
|
| Comprehensive documentation | ⚠️ PARTIAL | Architecture docs exist, deployment docs missing | **YES** 🔴 |
|
|
|
|
**Quality Completion**: 1 of 4 (25%)
|
|
|
|
### Operational Success Criteria (Line 36-40)
|
|
|
|
| Criterion | Status | Evidence | Gap? |
|
|
|-----------|--------|----------|------|
|
|
| **Docker deployment ready** | **❌ NOT MET** | **No Dockerfile exists** | **YES** 🔴 |
|
|
| **Simple SQLite backup strategy** | **❌ NOT MET** | **No backup script** | **YES** 🔴 |
|
|
| Health check endpoint | ✅ COMPLETE | /health endpoint working | No |
|
|
| Structured logging | ✅ COMPLETE | logging_config.py implemented | No |
|
|
|
|
**Operational Completion**: 2 of 4 (50%)
|
|
|
|
### Compliance Success Criteria (Line 42-44)
|
|
|
|
| Criterion | Status | Evidence | Gap? |
|
|
|-----------|--------|----------|------|
|
|
| W3C IndieAuth specification compliance | ⚠️ UNCLEAR | Core endpoints exist, not tested with real clients | **YES** 🔴 |
|
|
| OAuth 2.0 error responses | ✅ COMPLETE | Token endpoint has compliant errors | No |
|
|
| **Security headers and HTTPS enforcement** | **❌ NOT MET** | **Phase 4 not started** | **YES** 🔴 |
|
|
|
|
**Compliance Completion**: 1 of 3 (33%)
|
|
|
|
---
|
|
|
|
## Overall Success Criteria Summary
|
|
|
|
- **Functional**: 4/5 (80%) ⚠️
|
|
- **Quality**: 1/4 (25%) ❌
|
|
- **Operational**: 2/4 (50%) ❌
|
|
- **Compliance**: 1/3 (33%) ❌
|
|
|
|
**Total Success Criteria Met**: 8 of 16 (50%)
|
|
|
|
---
|
|
|
|
## Critical Gaps (Blocking v1.0.0 Release)
|
|
|
|
### 1. MISSING: Metadata Endpoint (P0 Feature)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: v1.0.0 roadmap line 62, Phase 3
|
|
- **Impact**: IndieAuth clients cannot discover endpoints programmatically
|
|
- **Effort**: XS (<1 day)
|
|
- **Specification**: W3C IndieAuth requires metadata endpoint for discovery
|
|
|
|
### 2. MISSING: Client Metadata Fetching (h-app microformat) (P0 Functional)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: Success criteria line 27, Phase 3 deliverables line 169
|
|
- **Impact**: Users cannot see what app they're authorizing (poor UX)
|
|
- **Effort**: S (1-2 days to implement microformat parser)
|
|
- **Specification**: IndieAuth best practice for client identification
|
|
|
|
### 3. MISSING: Security Hardening (P0 Feature)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: v1.0.0 roadmap line 65, entire Phase 4
|
|
- **Impact**: Application not production-ready, vulnerable to attacks
|
|
- **Effort**: S (1-2 days for implementation)
|
|
- **Components**:
|
|
- Security headers (X-Frame-Options, CSP, HSTS, etc.)
|
|
- HTTPS enforcement in production mode
|
|
- Input sanitization audit
|
|
- PII logging audit
|
|
|
|
### 4. MISSING: Security Test Suite (P0 Feature)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: Phase 4 lines 195-196, 204-217
|
|
- **Impact**: Unknown security vulnerabilities
|
|
- **Effort**: S (2-3 days)
|
|
- **Components**:
|
|
- Timing attack tests
|
|
- SQL injection tests
|
|
- XSS prevention tests
|
|
- Open redirect tests
|
|
- CSRF protection tests (state parameter)
|
|
|
|
### 5. MISSING: Deployment Configuration (P0 Feature)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: v1.0.0 roadmap line 66, Phase 5
|
|
- **Impact**: Cannot deploy to production
|
|
- **Effort**: S (1-2 days)
|
|
- **Components**:
|
|
- Dockerfile with multi-stage build
|
|
- docker-compose.yml for testing
|
|
- Backup script for SQLite
|
|
- Environment variable documentation
|
|
|
|
### 6. MISSING: Integration & E2E Test Suite (P0 Feature)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: v1.0.0 roadmap line 67, Testing Strategy, Phase 5
|
|
- **Impact**: No verification of complete authentication flow
|
|
- **Effort**: L (part of 10-14 day comprehensive test suite effort)
|
|
- **Components**:
|
|
- Integration tests for all endpoints (authorization, token, verification)
|
|
- End-to-end authentication flow tests
|
|
- OAuth 2.0 error response tests
|
|
- W3C IndieAuth compliance tests
|
|
|
|
### 7. MISSING: Real Client Testing (P0 Exit Criteria)
|
|
- **Priority**: CRITICAL 🔴
|
|
- **Requirement**: Phase 5 exit criteria line 252, Success metrics line 535
|
|
- **Impact**: Unknown interoperability issues with real IndieAuth clients
|
|
- **Effort**: M (2-3 days)
|
|
- **Requirement**: Test with ≥2 different IndieAuth clients
|
|
|
|
### 8. MISSING: Deployment Documentation (P0 Quality)
|
|
- **Priority**: HIGH 🔴
|
|
- **Requirement**: Phase 5, Release Checklist lines 443-451
|
|
- **Impact**: Operators cannot deploy or configure server
|
|
- **Effort**: M (2-3 days)
|
|
- **Components**:
|
|
- Installation guide (tested)
|
|
- Configuration guide (complete)
|
|
- Deployment guide (tested)
|
|
- Troubleshooting guide
|
|
- API documentation (OpenAPI)
|
|
|
|
---
|
|
|
|
## Important Gaps (Should Address)
|
|
|
|
### 9. LOW: Authorization Endpoint Integration Tests
|
|
- **Priority**: IMPORTANT ⚠️
|
|
- **Impact**: Authorization endpoint has only 29.09% test coverage
|
|
- **Effort**: Part of integration test suite (included in critical gap #6)
|
|
- **Note**: Core logic tested via unit tests, but HTTP layer not verified
|
|
|
|
### 10. LOW: Verification Endpoint Integration Tests
|
|
- **Priority**: IMPORTANT ⚠️
|
|
- **Impact**: Verification endpoint has only 48.15% test coverage
|
|
- **Effort**: Part of integration test suite (included in critical gap #6)
|
|
- **Note**: Core logic tested via unit tests, but HTTP layer not verified
|
|
|
|
---
|
|
|
|
## Minor Gaps (Nice to Have)
|
|
|
|
### 11. MINOR: External Security Review
|
|
- **Priority**: OPTIONAL
|
|
- **Requirement**: Phase 4 exit criteria line 218 (optional but encouraged)
|
|
- **Impact**: Additional security assurance
|
|
- **Effort**: External dependency, not blocking v1.0.0
|
|
|
|
### 12. MINOR: Performance Baseline
|
|
- **Priority**: OPTIONAL
|
|
- **Requirement**: Phase 5 pre-release line 332
|
|
- **Impact**: No performance metrics for future comparison
|
|
- **Effort**: XS (part of deployment testing)
|
|
|
|
---
|
|
|
|
## Effort Estimation for Remaining Work
|
|
|
|
| Gap | Priority | Effort | Dependencies |
|
|
|-----|----------|--------|--------------|
|
|
| #1: Metadata Endpoint | CRITICAL | XS (<1 day) | None |
|
|
| #2: Client Metadata (h-app) | CRITICAL | S (1-2 days) | None |
|
|
| #3: Security Hardening | CRITICAL | S (1-2 days) | None |
|
|
| #4: Security Test Suite | CRITICAL | S (2-3 days) | #3 |
|
|
| #5: Deployment Config | CRITICAL | S (1-2 days) | None |
|
|
| #6: Integration & E2E Tests | CRITICAL | M (3-5 days) | #1, #2 |
|
|
| #7: Real Client Testing | CRITICAL | M (2-3 days) | #1, #2, #5 |
|
|
| #8: Deployment Documentation | HIGH | M (2-3 days) | #5, #7 |
|
|
|
|
**Total Estimated Effort**: 13-21 days
|
|
|
|
**Realistic Estimate**: 15-18 days (accounting for integration issues, debugging)
|
|
|
|
**Conservative Estimate**: 10-15 days if parallelizing independent tasks
|
|
|
|
---
|
|
|
|
## Recommendation
|
|
|
|
### Current Status
|
|
|
|
**v1.0.0 MVP is NOT complete.**
|
|
|
|
The implementation has made excellent progress on Phases 1-3 (foundation, domain verification, and core IndieAuth endpoints), achieving 87.27% test coverage and demonstrating high code quality. However, **critical security hardening, deployment preparation, and comprehensive testing have not been started**.
|
|
|
|
### Completion Assessment
|
|
|
|
**Estimated Completion**: 60-65% of v1.0.0 requirements
|
|
|
|
**Phase Breakdown**:
|
|
- Phase 1 (Foundation): 100% complete ✅
|
|
- Phase 2 (Domain Verification): 100% complete ✅
|
|
- Phase 3 (IndieAuth Protocol): 75% complete (metadata endpoint + client metadata missing)
|
|
- Phase 4 (Security & Hardening): 0% complete ❌
|
|
- Phase 5 (Deployment & Testing): 10% complete (unit tests only) ❌
|
|
|
|
**Feature Breakdown**:
|
|
- P0 Features: 11 of 14 complete (79%)
|
|
- Success Criteria: 8 of 16 met (50%)
|
|
|
|
### Remaining Work
|
|
|
|
**Minimum Remaining Effort**: 10-15 days
|
|
|
|
**Critical Path**:
|
|
1. Implement metadata endpoint (1 day)
|
|
2. Implement h-app client metadata fetching (1-2 days)
|
|
3. Security hardening implementation (1-2 days)
|
|
4. Security test suite (2-3 days)
|
|
5. Deployment configuration (1-2 days)
|
|
6. Integration & E2E tests (3-5 days, can overlap with #7)
|
|
7. Real client testing (2-3 days)
|
|
8. Documentation review and updates (2-3 days)
|
|
|
|
**Can be parallelized**:
|
|
- Security hardening + deployment config (both infrastructure tasks)
|
|
- Real client testing can start after metadata endpoint + client metadata complete
|
|
- Documentation can be written concurrently with testing
|
|
|
|
### Next Steps
|
|
|
|
**Immediate Priority** (Next Sprint):
|
|
1. **Implement metadata endpoint** (1 day) - Unblocks client discovery
|
|
2. **Implement h-app microformat parsing** (1-2 days) - Unblocks consent UX
|
|
3. **Implement security hardening** (1-2 days) - Critical for production readiness
|
|
4. **Create Dockerfile + docker-compose** (1-2 days) - Unblocks deployment testing
|
|
|
|
**Following Sprint**:
|
|
5. **Security test suite** (2-3 days) - Verify hardening effectiveness
|
|
6. **Integration & E2E tests** (3-5 days) - Verify complete flows
|
|
7. **Real client testing** (2-3 days) - Verify interoperability
|
|
|
|
**Final Sprint**:
|
|
8. **Documentation review and completion** (2-3 days) - Deployment guides
|
|
9. **Release preparation** (1 day) - Release notes, final testing
|
|
10. **External security review** (optional) - Additional assurance
|
|
|
|
### Release Recommendation
|
|
|
|
**DO NOT release v1.0.0 until**:
|
|
- All 8 critical gaps are addressed
|
|
- All P0 features are implemented
|
|
- Security test suite passes
|
|
- Successfully tested with ≥2 real IndieAuth clients
|
|
- Deployment documentation complete and tested
|
|
|
|
**Target Release Date**: +3-4 weeks from 2025-11-20 (assuming 1 developer, ~5 days/week)
|
|
|
|
---
|
|
|
|
## Architect's Accountability
|
|
|
|
### What I Missed
|
|
|
|
I take full responsibility for prematurely declaring v1.0.0 complete. My failures include:
|
|
|
|
1. **Incomplete Phase Review**: I approved "Phase 3 Token Endpoint" without verifying that ALL Phase 3 requirements were met. The metadata endpoint was explicitly listed in the v1.0.0 roadmap (line 62) and Phase 3 requirements (line 162), but I did not catch its absence.
|
|
|
|
2. **Ignored Subsequent Phases**: I declared v1.0.0 complete after Phase 3 without verifying that Phases 4 and 5 had been started. The roadmap clearly defines 5 phases, and I should have required completion of all phases before declaring MVP complete.
|
|
|
|
3. **Insufficient Exit Criteria Checking**: I did not systematically verify each exit criterion from the v1.0.0 roadmap. If I had checked the release checklist (lines 414-470), I would have immediately identified multiple unmet requirements.
|
|
|
|
4. **Success Criteria Oversight**: I did not verify that functional, quality, operational, and compliance success criteria (lines 20-44) were met before approval. Only 8 of 16 criteria are currently satisfied.
|
|
|
|
5. **Feature Table Neglect**: I did not cross-reference implementation against the P0 feature table (lines 48-68). This would have immediately revealed 3 missing P0 features.
|
|
|
|
### Why This Happened
|
|
|
|
**Root Cause**: I focused on incremental phase completion without maintaining awareness of the complete v1.0.0 scope. Each phase report was thorough and well-executed, which created a false sense of overall completeness.
|
|
|
|
**Contributing Factors**:
|
|
1. Developer reports were impressive (high test coverage, clean implementation), which biased me toward approval
|
|
2. I lost sight of the forest (v1.0.0 as a whole) while examining trees (individual phases)
|
|
3. I did not re-read the v1.0.0 roadmap before declaring completion
|
|
4. I did not maintain a checklist of remaining work
|
|
|
|
### Corrective Actions
|
|
|
|
**Immediate**:
|
|
1. This gap analysis document now serves as the authoritative v1.0.0 status
|
|
2. Will not declare v1.0.0 complete until ALL gaps addressed
|
|
3. Will maintain a tracking document for remaining work
|
|
|
|
**Process Improvements**:
|
|
1. **Release Checklist Requirement**: Before declaring any version complete, I will systematically verify EVERY item in the release checklist
|
|
2. **Feature Table Verification**: I will create a tracking document that maps each P0 feature to its implementation status
|
|
3. **Exit Criteria Gate**: Each phase must meet ALL exit criteria before proceeding to next phase
|
|
4. **Success Criteria Dashboard**: I will maintain a living document tracking all success criteria (functional, quality, operational, compliance)
|
|
5. **Regular Scope Review**: Weekly review of complete roadmap to maintain big-picture awareness
|
|
|
|
### Lessons Learned
|
|
|
|
1. **Incremental progress ≠ completeness**: Excellent execution of Phases 1-3 does not mean v1.0.0 is complete
|
|
2. **Test coverage is not a proxy for readiness**: 87.27% coverage is great, but meaningless without security tests, integration tests, and real client testing
|
|
3. **Specifications are binding contracts**: The v1.0.0 roadmap lists 14 P0 features and 16 success criteria. ALL must be met.
|
|
4. **Guard against approval bias**: Impressive work on completed phases should not lower standards for incomplete work
|
|
|
|
### Apology
|
|
|
|
I apologize for declaring v1.0.0 complete prematurely. This was a significant oversight that could have led to premature release of an incomplete, potentially insecure system. I failed to uphold my responsibility as Architect to maintain quality gates and comprehensive oversight.
|
|
|
|
Going forward, I commit to systematic verification of ALL requirements before any release declaration.
|
|
|
|
---
|
|
|
|
## Conclusion
|
|
|
|
The Gondulf IndieAuth Server has made substantial progress:
|
|
- Strong foundation (Phases 1-2 complete)
|
|
- Core authentication flow implemented (Phase 3 mostly complete)
|
|
- Excellent code quality (87.27% test coverage, clean architecture)
|
|
- Solid development practices (comprehensive reports, ADRs, design docs)
|
|
|
|
However, **critical work remains**:
|
|
- Security hardening not started (Phase 4)
|
|
- Deployment not prepared (Phase 5)
|
|
- Real-world testing not performed
|
|
- Key features missing (metadata endpoint, client metadata)
|
|
|
|
**v1.0.0 is approximately 60-65% complete** and requires an estimated **10-15 additional days of focused development** to reach production readiness.
|
|
|
|
I recommend continuing with the original 5-phase plan, completing Phases 4 and 5, and performing comprehensive testing before declaring v1.0.0 complete.
|
|
|
|
---
|
|
|
|
**Gap Analysis Complete**
|
|
|
|
**Prepared by**: Claude (Architect Agent)
|
|
**Date**: 2025-11-20
|
|
**Status**: v1.0.0 NOT COMPLETE - Significant work remaining
|
|
**Estimated Remaining Effort**: 10-15 days
|
|
**Target Release**: +3-4 weeks
|